Turkmenistan completes the construction of the TAPI section Serhetabat – Herat

https://ussatnews.com/storage/posts/13994/original-16b05952feabaa.jpeg

The construction of the Afghan section of the TAPI transnational gas pipeline Serhetabat – Herat, called “Arkadagyň ak ýoly,” is nearing completion. According to TAPI Pipeline Company Limited, the pipeline has already approached Herat.

By the end of the year, construction and installation specialists will have to complete the laying and backfilling of the remaining pipes, to arrange passages, to build a gas measuring station and also to finalize the package of legal and commercial documents with the Afghan side. The start of natural gas supplies via this route is scheduled for 2027.

The construction of the 153-kilometer section from Turkmen Serhetabat to Afghan Herat began on September 11, 2024. In just over two years of cooperation with Afghan partners, the project has entered the final assembly stage. About 850 Turkmen specialists and more than 280 units of special equipment prepared 150.7 kilometers of right-of-way along the highway and 139 kilometers of pipes have already been welded and laid into a string – this is almost 90% of the entire length of the section. Hydrostatic tests are carried out step by step on the finished sections.

The TAPI is considered not just as a transit route with a capacity of up to 33 billion cubic meters of gas a year, but also as a base for the industrial development of the region. An important step in this direction was the memorandum of cooperation between the Türkmengaz State Concern and the Afghan state company Afghan Gas, signed on August 10, 2026, during the working visit of the National Leader of the Turkmen people to the province of Herat.

The parties have already identified priority infrastructure tasks for Herat: laying a gas pipeline to a local industrial park with the complete gasification of the industrial zone, constructing gas distribution stations and establishing a complex for the production of compressed natural gas (CNG).

Private capital is also showing interest in the project: one of the investors took the initiative to build a gas power plant near Herat. TAPI Pipeline Company Limited notes that synchronizing the gas pipeline with the planned power transmission lines and railways will reduce costs and form a single safe transport and energy corridor.

The raw material base of the main is the giant Galkynyş deposit. The start of work on the development of its fourth stage will provide additional 10 billion cubic meters of commercial gas a year. Simultaneously, preparations are underway for the next phases, including the third one. To explore the possibilities of cooperation in this direction, the Türkmengaz State Concern signed a confidentiality agreement with the Malaysian company Petronas.

An additional guarantee for international partners and investors is the status of permanent neutrality of Turkmenistan, three times confirmed by resolutions of the UN General Assembly and enshrined in the recently approved National Conception “International Law and Neutrality of Turkmenistan”.

The promotion of the TAPI project complements Ashgabat’s overall strategy to diversify export supplies – the development of southern, eastern and western directions, which insures the region from fluctuations in the global energy market. Thus, in the eastern direction, the Turkmenistan – China gas pipeline provided the supply of more than 477 billion cubic meters of gas for almost 17 years of operation (from December 2009 till October 1, 2026). The western vector was set by President Serdar Berdimuhamedov at the Consultative Meeting of the Heads of State of Central Asia and Azerbaijan in Avaza on October 8: Turkmenistan is ready to use its Caspian infrastructure, including the port of Turkmenbashi, for the multi-vector transit of gas and electricity. On the Caspian shelf, a long-term partnership is secured by a new production sharing agreement for Block 1 with the participation of Petronas and the Emirati company ADNOC XRG.

The commissioning of the Serhetabat – Herat section will be a key practical step in the implementation of the entire TAPI project, opening Turkmen gas access to one of the fastest growing energy markets in the world.

Ussa Ussayev,

Editor-in-Chief of the Nebit-Gaz newspaper.

Other articles
16ab744755266a.jpeg
The decisions of the Halk Maslahaty set new benchmarks for the development of Turkmenistan’s fuel and energy sector

The meeting of the Halk Maslahaty of Turkmenistan, held at the Maslahat Köşgi Palace in the capital on September 23 and chaired by the National Leader of the Turkmen people, Chairman of the Halk Maslahaty Gurbanguly Berdimuhamedov, summed up large-scale transformations and defined key tasks for the country’s socioeconomic and industrial development.


169083a25cc418.jpeg
Turkmenistan’s Green Energy Diplomacy

Throughout its centuries-old history, humankind has strived to be closer to nature and to treat its resources and clean environment with great care.


169082eb711208.jpeg
Green energy – prosperity of the future

One of the main differences between the use of green energy, i.e., the use of solar, wind and water energy, and the use of fossil fuels (oil, gas, coal and others) as energy is that their use practically does not cause pollution caused by the emission of methane and carbon dioxide into the atmosphere.

168c37ec2b1350.jpeg
Environmental well-being is the main requirement of the era

In the period of the Revival of the New Era of the Powerful State, the work carried out to protect the environment, to ensure environmentally friendly conditions, to reduce harmful emissions, to preserve the ozone layer and to rationally use natural resources is gaining momentum. Environmental safety is of great importance in ensuring a prosperous and peaceful life in the country.


168c37463e56b7.jpeg
Environmental well-being and green energy are a priority

As a result of the increase in population and production rates, the economy continues to develop.